A 600MWh Battery Goes Live for Meta. Utah's Data-Centre Race Is On

Lydian's 150MW Faraday battery is now serving Meta's Eagle Mountain campus, the clearest sign yet that power, not land, decides where Utah's data centres get built.

Illustrative photo: Olivier Bonin/SLAC National Accelerator Laboratory, CC BY 4.0, via Wikimedia Commons

A 150MW battery built to serve one hyperscale campus is now running in the Utah desert.

Lydian Energy's Faraday battery storage project has reached commercial operation, the developer said this week, under a long-term agreement with utility PacifiCorp and sized to support Meta's nearby Eagle Mountain data centre (Energy-Storage.News). The 150MW/600MWh system is the clearest sign yet that in Utah, power supply rather than land or fibre is becoming the deciding factor in where data centres get built.

Key takeaways

  • 150MW/600MWh: Lydian's Faraday battery is live in Utah, developed to support Meta's Eagle Mountain data centre under a long-term PacifiCorp agreement.
  • 307 Utah data-centre projects are still prospective, against just 57 under construction.
  • Meta's Eagle Mountain campus is already being expanded, and Taiyo pairs it with a new natural-gas power plant.
  • Two rivals are circling: O'Leary Ventures and a project linked to Valar Atomics are advancing competing Utah data-centre plans.

One Customer, One 600MWh Battery

Lydian Energy, which is backed by Excelsior Energy Capital, built the Faraday battery at its existing Utah County solar site. It runs under a long-term agreement with PacifiCorp, which uses the storage to firm up the grid that Meta's campus draws on.

The size is the story. A standalone 600MWh battery justified by a single data centre's load is a template, not a curiosity. Where utilities once added peaking plants to serve a large industrial customer, they can now contract for four hours of stored energy instead, and a private developer carries the construction and operating risk. For Meta, the battery turns an intermittent supply into a firm one without Meta owning generation. For PacifiCorp, it adds capacity to a strained grid without a new plant.

Meta's Eagle Mountain Campus Is Already Building

Meta's Eagle Mountain campus appears as a campus expansion under construction, developed alongside a new natural-gas power plant that will feed it (record). An earlier record dates the initial Eagle Mountain build to 2024 and notes local opposition over electricity demand and land use (record).

The campus is not a proposal. It is a build site with a power problem attached, and storage is now part of the answer.

At Eagle Mountain, half the tracked data-centre records are already building

Data-centre projects at Eagle Mountain, Utah, by stage

Data
Projects
Under construction14
Prospective14

Source: Taiyo records, data-centre projects at Eagle Mountain, Utah

Read the two local records together and a pattern appears: a campus whose demand is already large enough to justify a dedicated battery and, separately, a new gas plant. At Eagle Mountain the tracked pipeline is evenly split, with as many records under construction as prospective. That balance is unusual for Utah as a whole.

307 Utah Projects Proposed, 57 Under Construction

Statewide, the picture is mostly promise. Taiyo records 307 prospective data-centre projects in Utah, against 57 under construction and 14 closed. The prospective figure is a count of what we hold, including announced projects, early applications and proposals that have not yet reached construction. It is not a census of the market.

Only 57 of Utah's tracked data-centre projects have broken ground

Data-centre projects across Utah by stage

Data
Projects
Prospective307
Under construction57
Closed14
Failure4

Source: Taiyo records, data-centre projects in Utah

The tail of that chart carries its own signal. 14 are closed, meaning completed or concluded, and 4 sit in failure states, meaning cancelled, suspended or stalled. For a state with 57 live builds, fourteen completed projects show the sector has delivered, not only announced. Four failures show how many proposals do not survive to construction.

Two projects stand out in the queue. O'Leary Ventures' planned Stratos Data Hub appears in the records at the proposal stage (record). So does a planned AI campus linked to Valar Atomics and NVIDIA, billed as nuclear-powered (record). Both need generation that Utah's grid does not yet have.

Pouring concrete is not the bottleneck. Power is. When 307 projects sit on paper and only 57 are building, the constraint is the wire and the megawatt, not the land. The Faraday battery fills that gap for one customer, and it shows what the rest of the queue will need before it can move.

What to Watch in the Next 12 Months

Lydian is already planning a second phase at the Faraday site, according to the coverage, targeted for later this decade. The wider signal is whether Utah's 307 prospective projects begin converting into construction, and whether gas plants and storage keep pace. For contractors, suppliers and lenders, that shifts the work toward the power and interconnection layer around the data centre, not just the shell and the servers.

If you want to see which Utah data-centre projects are actually moving, and who is behind them, run your own question in ConstructChat at taiyo.ai.

Methodology

Project counts and project links come from Taiyo Canvas records for data-centre projects in Utah, USA, held as of November 2026, and are counts of what Taiyo holds rather than a census of the market. Records closed as tenders and other non-project statuses are excluded from the stage chart. Details of the Faraday battery come from Energy-Storage.News, which we relied on for this story.

How these numbers were produced

Every figure above is a count of records in the Taiyo Data Mesh, returned by one of the queries below on Nov 12, 2026. Counts are records as held in the Data Mesh, not deduplicated projects, and statuses are as recorded at query time. Contract and budget values are not used: summed across sources they mix currencies and include outliers, so they are not reliable as totals.

QueryFiltersRecords
Records by statusCountry: USA, Utah · Sector: Data Center461