Boise's Six-Month Data Center Moratorium: The 600 MW Bid Behind It

Boise became the latest US city to freeze large data centers, pausing approvals for six months. The project that set it off is roughly four times the size of the Meta facility the region already hosts.

Illustrative photo: Tobias Klenze, CC BY 3.0, via Wikimedia Commons

Boise has stopped accepting applications for large data centers, and the project that forced the vote is about four times the size of the Meta facility the region already hosts.

The Boise City Council voted unanimously on Nov. 10 to impose a six-month moratorium on new data centers of 100,000 square feet or larger, effective immediately (Idaho Capital Sun). The pause targets one proposal: a 600-megawatt campus that Rhea Data, a subsidiary of Nevada-based Arevia Power, wants to build on roughly 3,700 acres of Bureau of Land Management land south of the city (KTVB). At about 4 million square feet, it would dwarf Meta's Kuna facility nearby.

Key takeaways

  • Boise's six-month moratorium on large data centers took effect immediately after a unanimous council vote on Nov. 10.
  • The project behind it is Rhea Data's 600 MW bid on roughly 3,700 acres of federal land south of Boise.
  • Taiyo tracks 108 data center records in Idaho; 55 are prospective and only 21 are under construction.
  • Neither Rhea Data nor Arevia Power appears in our Idaho records, so the state's most-watched project sits outside today's tracked pipeline.

The 600 MW Bid Behind Boise's Freeze

The bid that forced the vote is Rhea Data's 600 MW campus on federal land south of the city. The mayor proposed the moratorium the Friday before the vote and framed it as a breather, not a ban. It "will put the brakes on hyperscale data centers in Boise, so it gives us the time to better determine and understand the impacts," the mayor said (East Idaho News). More than 100 residents turned out for a hearing that ran about an hour, with testimony such as "Don't sell off our future to the highest bidder."

The council set the trigger at projects of 100,000 square feet or larger, or those drawing 20 megawatts (Idaho Capital Sun). Local coverage differs on the power figure, with one station reporting a threshold of 200 megawatts instead (KIVI). Either way, the Rhea Data campus clears it with room to spare. The geography matters too: the site sits on federal land, which puts the city on the edge of a decision it does not fully control.

Idaho's Pipeline Is Nuclear Before It Is Hyperscale

Most of Idaho's tracked pipeline has not broken ground. Taiyo holds 108 data center records in Idaho: 55 prospective, 29 closed, 21 under construction and 3 in failure states. The forward pipeline is real, but it is early.

Most of Idaho's data center pipeline is still on the drawing board

Data center records in Idaho by stage

Data
Records
Prospective55
Closed29
Under construction21
Failure3

Source: Taiyo records, data center projects and tenders in Idaho

The sponsors are the surprise. The largest single backer of Idaho data centers in our records is not a hyperscaler but the U.S. Department of Energy, tied to nuclear-powered computing at the Idaho National Laboratory. Aalo Atomics and Oklo follow, and Meta ranks fifth. That is a different race from the one Boise is pausing, and it runs on reactors, not the grid the city is worried about.

Federal nuclear programs anchor more of Idaho's pipeline than any hyperscaler

Idaho data center records by sponsor or developer

Data
Records
U.S. Dept. of Energy16
Aalo Atomics5
Idaho National Laboratory3
Oklo3
Meta2
Matrix Renewables2
NRG2
T5 Data Centers2

Source: Taiyo records, data center projects and tenders in Idaho

The commercial side is thinner and more uneven. ValorC3's Boise Greenfield Hyperscale Data Center Campus is the one commercial project already under construction (record), the kind of build the moratorium now freezes behind it. Diode Ventures' planned Kuna facility sits on hold (record), a sign that several proposals were waiting on power and land even before the vote. Meta's own Kuna build is the anchor at scale (record). Sponsors are not recorded for every project, so treat this as where activity clusters, not a full census.

Boise Is Not the First Idaho City to Pause

Boise is joining a pattern, not starting one. Our records already carry a Bannock County data center moratorium in the Pocatello area and a statewide Idaho Data Center Regulatory Framework (record). A six-month freeze in the capital makes three regulatory signals in a single state.

For the people who build, supply and finance these projects, the signal is timing risk, not demand risk. A moratorium delays the permitting clock and pushes financial close to the right. Contractors weighing Idaho should treat the next two quarters as a diligence window: track which projects clear review, which sponsors hold their land, and whether the city's threshold lands at 20 or 200 megawatts, because that one number decides how many projects even qualify.

The Federal Land Boise Cannot Pause

The decisive test is the Rhea Data proposal itself. It sits on federal land, outside Boise's direct control, so a city moratorium may slow local politics without stopping the project. Whether the campus advances, stalls, or enters our records will say more about Idaho's data center market than the vote did.

Run your own question in ConstructChat at taiyo.ai to see which Idaho projects clear review and how the pipeline shifts.

Methodology

This article draws on Taiyo records for data center projects and tenders in Idaho, as of November 2026. The stage breakdown covers 108 records across prospective, closed, under construction and failure statuses. The sponsor ranking counts Idaho data center records by sponsor or developer, where a sponsor is recorded; sponsors are not recorded for every project, so the ranking shows where activity clusters rather than a full census. Event details come from Idaho Capital Sun, KTVB, KIVI and East Idaho News.

How these numbers were produced

Every figure above is a count of records in the Taiyo Data Mesh, returned by one of the queries below on Nov 12, 2026. Counts are records as held in the Data Mesh, not deduplicated projects, and statuses are as recorded at query time. Contract and budget values are not used: summed across sources they mix currencies and include outliers, so they are not reliable as totals.

QueryFiltersRecords
Records by statusCountry: USA · Sector: Data Center · Record type: Project22,686
Records by statusCountry: USA, Idaho · Sector: Data Center108
Records by statusCountry: USA, Idaho · Sector: Data Center · Search: sponsor developer2

Follow us on LinkedIn for more updates.