Vineyard Wind 1, the first large-scale offshore wind farm built in the United States, came fully online on 29 October, and Revolution Wind reached full power days later. For the first time, two major offshore wind farms are delivering into New England's grid together, and the pair answers the question the region has asked for a decade: whether offshore wind at scale can actually reach the socket.
The two farms now supply more than 1,500 MW, enough for roughly 750,000 homes. Both sit in federal waters off southern New England, one south of Martha's Vineyard, the other between Rhode Island and Connecticut. On a peak afternoon this week, all wind sources were supplying about 856 MW to the regional grid at once, as reported by WWLP.
Key takeaways
- More than 1,500 MW now flows from Vineyard Wind 1 and Revolution Wind into New England's grid.
- Vineyard Wind 1 is an 800 MW, 50-50 venture of Avangrid Renewables and Copenhagen Infrastructure Partners.
- Ørsted and Eversource's Revolution Wind, at 704 MW, reached full power only after a year lost to federal roadblocks.
- A queue is waiting: our records list several New England projects still under development.
Two Farms, 800 MW and 704 MW, One Grid
Vineyard Wind 1 is the larger of the pair at about 800 MW across 62 turbines, sited roughly 15 miles south of the Massachusetts coast. Massachusetts utilities buy its output, and Copenhagen Infrastructure Partners is the sponsor on the record we hold for the project.
Revolution Wind adds 704 MW from about 60 Siemens Gamesa turbines, roughly 15 miles south of the Rhode Island coast. Rhode Island contracted 400 MW and Connecticut 304 MW on 20-year terms. Reports put the project's cost near $6.2 billion, and it recovered from a year-long delay to reach full output, per WBUR.
Two farms now deliver more than 1,500 MW to New England
Operating capacity of New England's two newest offshore wind farms
Data
| Capacity | |
|---|---|
| Vineyard Wind 1 | 800 |
| Revolution Wind | 704 |
Source: News coverage of Vineyard Wind 1 and Revolution Wind
Revolution Wind's output is shared between the two states that signed for it, which is why the project counts twice in the region's power plans.
Revolution Wind's 704 MW is split between two states
Contracted offtake by state
Data
| Contracted MW | |
|---|---|
| Rhode Island | 400 |
| Connecticut | 304 |
Source: News coverage of Revolution Wind offtake
Ørsted and Avangrid Are Not Alone in This Queue
Our records show the region's pipeline is far from finished. Community Offshore Wind 1 and Community Offshore Wind 2 sit under development, alongside Leading Light and Bluepoint Wind. A separate record tracks 3.5 GW of contracted offshore wind projects in New England.
These are announced, not built. They are the projects that will compete for the same ports, the same installation vessels and the same cable supply chain that Vineyard Wind 1 and Revolution Wind just consumed. For a bid director or a supplier, that queue is the real signal: the two farms now spinning off New England are the proof of concept for everything behind them.
The development base behind that queue is concentrated. Ørsted, Avangrid and Eversource, the names tied to Revolution Wind, are the same organisations our records link to a large share of the Northeast's wind activity. A small group of developers and utilities controls most of what could be built next.
The Turn: A Recovery the Sector Needed
The milestone matters most because of how close it came to not happening. Revolution Wind lost roughly a year to a federal push to halt construction, and states had to go to court to restart work before it reached full power. Two fully operating farms now stand as evidence that the Northeast's offshore pipeline, though slowed, is real and deliverable.
That is a different message from the one the sector carried through the permitting fights. Lenders, EPC contractors and marine suppliers priced in delay risk and shutdown risk across the whole region. Vineyard Wind 1 and Revolution Wind reaching full output does not erase that risk, but it changes the reference case from "will these get built" to "when will the next ones start".
For governments, the two farms also settle a procurement question. The clean energy contracts signed years ago have now produced power, which strengthens the case for the next round of state solicitations.
What to Watch Next
Watch the offtake rounds and the financial close dates behind Community Offshore Wind, Leading Light and Bluepoint Wind. Those are the moments that convert a queue into steel in the water, and the contractors and lenders who move early on them will set the terms for the next wave.
We track the projects, tenders and sponsors across this pipeline as they move. To see who is lined up behind New England's two newest farms, run your own question in ConstructChat at taiyo.ai.
How these numbers were produced
Every figure above is a count of records in the Taiyo Data Mesh, returned by one of the queries below on Nov 12, 2026. Counts are records as held in the Data Mesh, not deduplicated projects, and statuses are as recorded at query time. Contract and budget values are not used: summed across sources they mix currencies and include outliers, so they are not reliable as totals.
| Query | Filters | Records |
|---|---|---|
| Records by status | Country: USA · Sector: Wind · Search: offshore | 3,037 |
| Records by status | Country: USA · Sector: Wind | 97,047 |
| Records by status | Sector: Wind · Country: USA, Massachusetts, Rhode Island, Connecticut, New York, New Jersey, Maine, Virginia · Search: offshore · Record type: Project | 1,623 |
Follow us on LinkedIn for more updates.