A windowless data centre building with cooling stacks

Insights · Data ·

Telus Exits Vancouver's AI Data Centres. Who Builds Them Now?

Six months after unveiling a sovereign AI cluster with Ottawa, Telus walked away from two Vancouver data centres. Our records show the pipeline was announced long before it was built.

Illustrative photo: Kecko from Eastern Switzerland, CC BY 2.0, via Wikimedia Commons

The fanfare was in May 2026. By mid-November, Telus had walked away from two Vancouver AI data centres it unveiled with the Government of Canada and developer Westbank. Telus offered no reason. Westbank says it will carry on with a new partner it has not yet named.

The two sites, at 150 West Georgia Street downtown and 111 East 5th Avenue in Mount Pleasant, were planned to reach more than 150 MW of capacity by 2032, drawing an initial 85 MW from BC Hydro. That scale, concentrated in one metro market, is why the exit matters. It removes the anchor tenant from a flagship of Ottawa's sovereign AI build.

Key takeaways

  • Telus cancelled its role in two Vancouver AI data centres in November 2026, six months after a May announcement with the Government of Canada and Westbank.
  • British Columbia holds 41 prospective data centre projects against just 13 under construction, so most planned capacity is still paper.
  • Telus appears on 16 Canadian data centre project records, more than any other commercial developer, ahead of TransAlta's 14 and Equinix's 8.
  • The Kamloops expansion, to 20 MW by 2028, is unaffected and still proceeds.

Ottawa's AI Flagship Loses Its Anchor Tenant

In May 2026, Telus and the federal government presented a cluster of AI data centres: an expansion at Kamloops plus the two new Vancouver sites, pitched as a sovereign AI factory and backed through the federal innovation department, with the build framed as company and investors spending $1B. Vancouver's mayor endorsed it.

The project then met organised opposition, including the No AI Vancouver campaign. British Columbia capped new BC Hydro supply to data centres at 200 MW a year for two years from 2026. CBC and the Vancouver Sun reported the pull-out as a "confluence of factors." Telus has said only that it remains committed to compute infrastructure in Canada and will share more on its AI strategy later.

Our records show the same project fragmented across several announcement-stage entries, most of them prospective, with only the broader BC cluster captured as under construction. That thin paper trail is the tell. The deal was public long before it was firm.

In British Columbia, 41 Are Announced and 13 Are Building

British Columbia's data centre pipeline is mostly announced, not built

Data centre projects in British Columbia by status

Data
Projects
Prospective41
Under construction13
Closed9

Source: Taiyo records, data centre projects in British Columbia

The gap between announced and building is not unique to Vancouver. Across Canada, Taiyo holds 395 prospective data centre projects against 91 under construction. The sector's published pipeline runs years ahead of its steel. For contractors and suppliers, that changes the sales motion: the near-term awards sit with the 13 BC projects already in construction, not the 41 still on paper.

Telus Led the Commercial Field Before It Left

Telus led Canada's commercial data centre field before it stepped back

Commercial developers named on data centre project records in Canada

Data
Projects
Telus16
TransAlta14
Equinix8
Crusoe4
Allied2
Westbank1

Source: Taiyo records, data centre projects in Canada

Among commercial developers, Telus appears on more Canadian data centre project records than any rival. Equinix follows with 8 and Crusoe with 4. The turn is this: the most-tracked private developer in the sector is now withdrawing from its own marquee project. An exit at the top of the leaderboard signals that discipline, not shortage of ambition, is shaping the next phase of Canadian AI capacity.

What to Watch Next

Westbank's unnamed new partner is the first signal to track. So is whether the two Vancouver sites survive the provincial supply cap. The Kamloops expansion to 20 MW by 2028 travels on its own, and Telus's stated pivot toward connectivity and sovereign compute for Canadian business and government is a bet worth watching in its own right.

To see which other sponsors are lining up behind BC's announced data centres, or what a specific developer is building elsewhere, run your own question in ConstructChat at https://taiyo.ai.

How We Counted

Record counts come from Taiyo Canvas, our knowledge graph of global infrastructure, filtered to the data centre sector and, where stated, to British Columbia or Canada. Counts are what Taiyo holds, not a census of every project. Market size figures for the Vancouver project come from news coverage, cited above.

How these numbers were produced

Every figure above is a count of records in the Taiyo Data Mesh, returned by one of the queries below on Nov 18, 2026. Counts are records as held in the Data Mesh, not deduplicated projects, and statuses are as recorded at query time. Contract and budget values are not used: summed across sources they mix currencies and include outliers, so they are not reliable as totals.

QueryFiltersRecords
Records by statusCountry: CAN · Sector: Data Center5,427
Records by statusCountry: CAN, British Columbia · Sector: Data Center · Record type: Project63
Records by statusCountry: CAN · Sector: Data Center · Record type: Project655

Follow us on LinkedIn for more updates.